The Budget and Schedule Worksheet captures the project timing and
estimated cost by phase and total. With the Resource Management
option the Budget
& Schedule worksheet includes a section for capturing high level
resource requirements (by skill set). The worksheet automatically
calculates human resource cost by phase using standard resource costs
entered in the central resource pool. Other non-capital and capital
costs can be added for a complete cost profile for the project.
In this example "S" represents the start of the project; the subsequent
gates are numbered sequentially from 1 to 6 in this case. The Project
File can handle up to seven phases and eight gates or major milestones.
The phase names are indicated: "Investigation", "Feasibility" etc. The
phase-gate terminology can be adjusted based on the type of project
being managed.
Resources can be assigned to the project by skill set on this worksheet
if the Resource Management option is purchased. Only resource types that have been entered into the central resource pool can be assigned to the project. The resource pool captures standard
resource cost which is used to calculate the cost contribution to the project based on the headcount numbers entered (the example above shows a software engineer headcount of 2 for the 48 week development phase. This represents 96 person-weeks of effort
and is costed accordingly).
When the project is first created, preliminary timing estimates provide the
basis for the gate dates and phase durations. Similar preliminary estimates
are made for resources and project costs. These estimates are refined and
updated as the project proceeds through it's early phases. Once the
"baseline gate" is passed the project team is committed to the targets
established for the project and their performance is measured against those
targets.